through the study of smelting and continuous casting of High-Nitrogen stainless steel 10Cr21 Mnl6NiN
the two-step smelting and continuous casting technology has been optimized
the adding nitrogen rate is raised from 5 x 10
-6
~ 10 x 10
-6
/min to 20 x 10
-6
~ 30 x 10
-6
/min in later stages of LF
the LF refining time is shortened from 390 min to 240 min
the CCM steel waiting time is reduced from 4 h to 2 h ; it solves the problem of slag spilling during the nitrogen adding;it also avoids the billet buckling during continuous casting
the breakage rate of No. 1
&
No. 2 casting strand reduces from 100% to O
the equipment accident rate decreases from 66. 7% to 0
to achieve 100% 2- heats sequence casting. The practice shows that the billet casting without closely spaced rolls can produced Hig
h-Nitrogen stainless steel even though with only one five-high withdrawing and straightening machine.